1.6.6.2
Measurement
The cutoff portion of any pile will be measured for payment at the rate of
50 percent of the applicable contract unit price, and no other measurement
or payment will be made for such cutoff.
1.6.6.3
Unit of Measure
Unit of measure:
each.
[1.6.7
Pulled Piles
]1.6.7.1
Payment
Payment will be made for satisfactorily driven piles which are pulled at
the direction of the Contracting Officer and found to be in good condition.
Payment will be made for pulled timber piles which are replaced with new
piles. Where piles are pulled at the direction of the Contracting Officer
and found to be damaged, no payment will be made for originally furnishing
and driving such piles nor for the operation of pulling, and damaged piles
shall be replaced by new piles for which payment will be made.
1.6.7.2
Measurement
Satisfactorily driven piles which are pulled at the direction of the
Contracting Officer and found to be in good condition will be measured for
payment at the applicable contract unit price for furnishing and driving
the pile at its original position plus 50 percent of this amount to cover
the cost of pulling. Pulled timber piles shall not be redriven, but
replaced by new piles which will be measured for payment at the applicable
contract unit price for the lengths driven. Where piles are pulled at the
direction of the Contracting Officer and found to be damaged, no
measurement for payment will be made for originally furnishing and driving
such piles nor for the operation of pulling, but the damaged piles shall be
replaced by new piles which will be measured for payment at the applicable
contract unit price for the lengths driven.
1.6.7.3
Unit of Measure
Unit of measure:
linear meter foot.
PART 2
PRODUCTS
2.1
MATERIALS
2.1.1
Piles
**************************************************************************
NOTE: Specify the minimum butt or tip circumference
of the pile. For bearing piles, use the butt
circumference for a friction pile and use tip
circumference for an end-bearing pile. Clean-peeled
treatment is required.
**************************************************************************
Provide Douglas fir or Southern pine [clean-peeled] [rough-peeled],
[treated] [and] [untreated] piles conforming to ASTM D 25 and other
requirements as specified. Piles shall be in one piece of the length[s]