Work Plan within [30] [_____] calender days after notice to
proceed. No work at the site, with the exception of site
inspections and surveys, shall be performed until the Work Plan is
approved. The Contractor shall allow [30] [_____] calender days
in the schedule for the Government's review. No adjustment for
time or money will be made if resubmittals of the Work Plan are
required due to deficiencies in the plan. At a minimum, the Work
Plan shall include:
a.
Schedule of activities.
b.
Method of excavation and equipment to be used.
c.
Shoring or side-wall slopes proposed.
d.
Dewatering plan.
e. Storage methods and locations for liquid and solid
contaminated material.
f.
Borrow sources and haul routes.
g.
Decontamination procedures.
h.
Spill contingency plan.
Closure Report[; G][; G, [_____]]
[_____] copies of the Closure Report within [14] [_____]
calender days of work completion at the site.
SD-06 Test Reports
Surveys[; G][; G, [_____]]
Confirmation Sampling and Analysis[; G][; G, [_____]]
Sampling of Stored Material[; G][; G, [_____]]
Sampling Liquid[; G][; G, [_____]]
Compaction[; G][; G, [_____]]
Test results.
1.4
SURVEYS
Surveys shall be performed immediately prior to and after excavation of
contaminated material to determine the volume of contaminated material
removed. Surveys shall also be performed immediately after backfill of
each excavation. The Contractor shall provide cross-sections on [7.6]
[_____] meter [25] [_____] foot intervals and at break points for all
excavated areas. Locations of confirmation samples shall also be surveyed
and shown on the drawings. Surveys shall be performed in accordance with
Section: [_____].
1.5
REGULATORY REQUIREMENTS
1.5.1
Permits and Licenses
**************************************************************************
NOTE: Include additional site specific requirements
SECTION 02111
Page 7