USACE / NAVFAC / AFCESA
UFGS-02111 (September 2003)
----------------------------
Preparing Activity: USACE
Superseding
UFGS-02111 (September 2001)
GUIDE SPECIFICATION FOR CONSTRUCTION
References are in agreement with UMRL dated 23 June 2005
**************************************************************************
SECTION 02111
EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL
09/03
**************************************************************************
NOTE: This guide specification covers the
requirements for excavation, handling, and temporary
storage of contaminated material.
Comments and suggestions on this guide specification
are welcome and should be directed to the technical
proponent of the specification. A listing of
technical proponents, including their organization
designation and telephone number, is on the Internet.
Recommended changes to a UFGS should be submitted as
a Criteria Change Request (CCR).
Use of electronic communication is encouraged.
Brackets are used in the text to indicate designer
choices or locations where text must be supplied by
the designer.
**************************************************************************
PART 1
GENERAL
**************************************************************************
NOTE: The following information should be shown on
a. Overall site plan, borrow areas, stockpile
areas, storage areas, security requirements, special
shoring requirements, boring logs, and access routes.
b. Individual site plans of each area of
roads, utilities, topography, trees, shrubs, surface
conditions, etc.
c. Limits of pavement removal, fence removal, and
the location of ancillary equipment to be removed.
All specific chemical testing procedures (including
air emissions analysis) should be addressed in the
SECTION 02111
Page 3